Crossrail planned to open between October 2020 and March 2021

A new plan to complete the outstanding works and bring the Elizabeth line into passenger service at the earliest possible date has been developed by the new Crossrail leadership team. The high-level plan to complete the railway has progressed into a logically linked and detailed Delivery Control Schedule. Around 120 key milestones have now been identified and are being tracked.

The complexity of the remaining work, Crossrail Ltd has identified a six-month delivery window between October 2020 and March 2021 giving Londoners with a realistic and achievable scale for delivery.